Project 15 – Entry Control Facility Replacement

 

Entry Control Facility Replacement

Type: Commercial
Project: Entry Control Facility Replacement
Scope: Renovation
Value: $4.5MM
Duration: 11 Months

Description:  Design-build project to complete renovations to the Mississippi Gate Entry Control Facility at the Buckley Air Force Base.

Project Scope:

  • Design-build
  • Demolition of existing Entry Control Facility and associated infrastructure and pavements
  • Complete all civil work, including grading and drainage improvements, new asphalt pavements, curb and gutter, sidewalks, passive and active barrier installation, speed tables and bollards
  • Construction of new Entry Control House requiring cast-in-place foundations, structural steel, HVAC, plumbing, all utility services and interior finishes, facility includes rest rooms, administration area, communications room and storage
  • Install site electrical power, new traffic control signals, lighting and communications service

Challenges:

  • Active military base; all employees required security clearance
  • Worksite remained active and fully operational during construction
  • Multiple and deeply-tiered oversight
  • Fast-track design and construction schedule

 